Close

Sediment management

India - Tehri

Key project features

Category

Reduce sediment production (watershed management)

Reservoir volume:

3,540 Mm³ (original)

Installed capacity:

2,400 MW

Date of commissioning:

2006

The Tehri dam, in the north of India, was commissioned in 2006 to provide water for electricity generation, irrigation and drinking water. It has a sediment trap efficiency of 95 per cent and was designed to offset 150 years of sedimentation. Watershed management is the principle measure in use for reducing the sediment inflow into the Tehri reservoir.

Aerial view of the Tehri dam
Aerial view of the Tehri dam

The Tehri hydroelectric power complex, located in the Himalayan foothills, is owned and operated by the Tehri Hydro Development Corporation, a joint venture by the government of India and the government of Uttar Pradesh. The USD 1 billion complex comprises the 1,000 MW Tehri hydropower plant, the 400 MW Koteshwar plant (commissioned in 2012) and the 1,000 MW Tehri pumped storage plant (expected to be commissioned in 2018). See the hydroelectric complex aerial view in figure 1.

The Tehri reservoir serves multiple purposes besides storing water to produce 6,200 GWh of annual electricity generation. It provides irrigation to an additional area of 270,000 hectares as well as supporting the existing irrigated area of 604,000 hectares. It supplies clean drinking water to about 4 million people in Delhi and 3 million people in Uttar Pradesh and Uttarakhand. And last but not least, the Tehri reservoir has a flood control pool capacity of 219.65 Mm3.

The Tehri dam, a 260.5 m-high earth and rockfill dam, impounds water 44 km along Bhagirathi River and 25 km along Bhilangana River, creating a dead storage of 925 Mm3 and live storage of 2,615 Mm3, making a total storage capacity of 3,540 Mm3. Impoundment commenced in 2005. The Tehri reservoir operates between a 835 masl maximum operating level and a 740 masl minimum operating level. The crest elevation is 815 masl and together the chute spillway (see figure 2) and the four vertical shaft spillways have a discharge capacity of 15,540 m3/s.

The Tehri underground powerhouse hosts four Francis turbines of 250 MW each, which benefit from a gross head of 231.50 m. The power plant has a design power discharge of 584 m3/s.

Hydrology and sediments

The catchment tributary to the Tehri dam comprises 7,691 km2 and forms part of the Himalayan mountain range, and is characterised by four months of a rainy season called ‘monsoon’. The monsoon lasts from June to September, with July and August considered the peak flow period. Both the Bhagirathi and the Bhilangana Rivers originate from a glacier. The annual average precipitation varies from 1,016 mm to 2,630 mm during the rainy season, when the 40-60 per cent of annual rainfall occurs. The Tehri reservoir is designed to store the surplus flow during the monsoon season, resulting in about one-third of the average annual water yield of the Bhagirathi River - about 2,615 Mm3 - being stored in the Tehri dam.

The fragile geology and topographical features of the catchment, with its steep slope valleys, combined with development activities such as deforestation and terrace cultivation, have increased the rate of erosion in the area. The Bhagirathi River transports large amounts of sediment, and the mean annual suspended sediment load is 6.8 Mt. The river bed material consists of boulders, sand, and silt. The most significant sediment transport occurs during the rainy season. The specific annual sediment yield in the watershed is 907 t/km2. The Brune curve estimates the trap efficiency of the Tehri dam to be 95 per cent.

Sediment problems

In 2008, the study ‘Impacts of Tehri dam lessons learnt’, prepared by the Water for Welfare Secretariat at the Indian Institute of Technology Roorkee found that sedimentation will reduce the water storage capacity of the reservoir, having an impact on all of the benefits it currently provides.

During the planning phase of the Tehri dam back in the 1970s, the design did not include any sediment management strategy to route or remove sediments from the reservoir. It was designed with a traditional approach to offset 150 years of sedimentation. The lack of sediment data prevented accurate estimations of suspended sediment load and sedimentation rate.

The design sediment rate was estimated at 6.08 Mm3 per year. Since commissioning of the dam, two bathymetric surveys, one in 2008 and the latest in 2013, were carried out and, as a result, the sediment rate was estimated at 5 Mm3 per year. Currently, the total storage capacity is 3,506 Mm3 and the live storage capacity is 2,598 Mm3. According to the results from the bathymetric surveys, the dam could offset up to 185 years of sedimentation without implementing any sediment management strategic under the current climate and land conditions.

In 2011, a study calculated the sedimentation rate in the reservoir based on satellite imagery. The study determined the loss of storage capacity derived from the water-spread area at different elevations and the corresponding original and revised capacities. However, the results only show the loss of capacity from 2006 to 2011 in the study zone between 823 masl and 763 masl. The average loss rate computed in this live zone is higher than the average sediment rate estimated from the bathymetric surveys to the Tehri reservoir.

Sediment management strategies

Following the impact assessment studies, watershed management was the mitigation measure taken to reduce soil erosion and therefore reduce sediment inflow into the reservoir.

According to the results from the bathymetric surveys, the dam could offset up to 185 years of sedimentation without implementing any sediment management strategic under the current climate and land conditions."

The Catchment Area Treatment (CAT) plan was applied in areas of high to very high erosion, in total covering 52,204 hectares, including 44,157 hectares of forest land and the 8,047 hectares of agricultural land. The CAT works comprised afforestation, soil conservation, treatment of agriculture land, farm forestry and horticulture.

The soil erosion in the rim area of the reservoir is monitored between 850 masl and 1,050 masl. This monitoring programme aims to protect and regenerate vegetation in this area to reduce soil erosion and enhance the landscape to support tourism. The relative success of this approach is still to be determined.

Graphs and figures

Figure 1 - aerial view of the Tehri hydropower project (Google Earth)

Figure 2 - Tehri dam chute spillway

Download case study PDF file

2024 World Hydropower Outlook. The 2024 World Hydropower Outlook is the hydropower sector's flagship report that charts a course to deliver net zero. Read More
Privacy Policy